EASTERN THROUGH AREA POJECT (ETAP) CELEBRATES 20 YEARS OF PRODUCTION

July 19, 2018

BP reported that the Eastern Trough Area Project (ETAP) North Sea development, labelled by the Oil & Gas Authority (OGA) as the “poster child” for its Maximising Economic Recovery (MER UK) strategy, celebrates 20 years of production today, with the key hub expected to operate into the mid-late 2030s.
ETAP ranks as one of the largest and most commercially complex North Sea oil and gas developments of the past 20 years; multiple fields with varying ownership sharing a central processing facility (CPF). BP operates six of the seven ETAP fields; Machar, Madoes, Mirren, Mungo, Monan and Marnock. The other field is Heron.
At the time of development, the individual reservoirs were not deemed to be commercially viable on a stand-alone basis, so the ETAP alliance was formed to develop the fields as one joint development.
It came on stream in July 1998 with an estimated production life of 20 years. However, a $1billion investment programme in 2015 breathed new life into the hub, securing its future well into the 2030s.
Intially seven fields, four operated by BP and three by Shell produced through the CPF. Two further BP-operated fields came online four years later in 2002, bringing the total number of fields producing through the CPF to nine. Two of the Shell fields have since ceased production. Day-to-day production operations of the remaining seven ETAP fields are controlled by BP from the CPF.
In its two decades of operations, more than 550 million barrels of oil equivalent (gross) has been produced from the BP-operated ETAP fields.
BP North Sea Regional President Ariel Flores said: “ETAP embodies the pioneering and innovative spirit the North Sea is renowned for around the world and shows what can be achieved when companies work together for the greater good of the region. When the project was sanctioned in the mid-1990s, BP and our ETAP joint venture partners were applauded for our unique collaboration and high level of innovation. Here we are 20 years later, continuing to push boundaries in maximising recovery and extending field-life. ETAP remains a key asset in BP’s refreshed North Sea portfolio and our enduring North Sea presence.” (Source: BP)