SECOND STAGE OF EGYPT’S WEST NILE DELTA DEVELOPMENT ON STREAM

BP announced first gas production from the second stage of its West Nile Delta development offshore Egypt.
The project, which produces gas from the Giza and Fayoum fields, was developed as a deepwater, long-distance tie-back to an existing onshore plant. The successful startup is the second in a string of new upstream major projects expected to be brought on line in 2019 for BP.
Bob Dudley, BP chief executive, said: “With the second stage of West Nile Delta now online, BP has now safely brought 21 new upstream major projects into production over the last three years, keeping us on track to deliver 900,000 barrels of oil equivalent per day by 2021. With the second stage of West Nile Delta now online, BP has now safely brought 21 new upstream major projects into production over the last three years, keeping us on track to deliver 900,000 barrels of oil equivalent per day by 2021.”
The West Nile Delta development includes a total of five gas fields across the North Alexandria and West Mediterranean Deepwater offshore concession blocks. It was originally planned as two separate projects, but BP and its partners realized the opportunity to deliver it in three stages, accelerating delivery of gas production commitments to Egypt.
Stage one of the project, which started producing in 2017, included gas production from the first two fields, Taurus and Libra. The Giza and Fayoum development, which includes eight wells, is currently producing around 400 million cubic feet of gas per day (mmscfd) and is expected to ramp up to a maximum rate of approximately 700 mmscfd.
The third stage of the West Nile Delta project will develop the Raven field. Production is expected in late 2019. (Source: BP)