SUCCESFUL APPRAISAL OF THE MAKO GAS FIELD IN THE WEST NATUNA BASIN
Coro Energy, the Southeast Asian focused upstream oil and gas company, is pleased to provide an operational update in relation to the drilling campaign in the Duyung PSC in the West Natuna basin, offshore Indonesia, in which Coro holds a 15% interest. The Duyung PSC is operated by West Natuna Exploration Ltd (WNEL).
Tambak-1, located approximately 4.5 km north of the Mako South-1 well, has been drilled to an intermediate depth of 513 metres true vertical depth sub-sea. The well has intersected the intra-Muda reservoir of the Mako field and a full suite of wireline logs have been acquired together with a pressure survey and extensive fluid and gas samples recovered. These data have established the well as a successfull appraisal of the Mako gas field and confirm the large, areally extensive single tank model for the field.
Highlights
• Top reservoir depth came in at circa 389 metres TVDSS as predicted
• A very well developed upper sandstone unit of approximately 5.2 metres with wireline logs showing excellent porosity & permeabilities
• The well encountered a much better developed intra-Muda sand package than expected. In addition to the upper unit, a thick, lower sandstone unit of almost 20 metres was found, providing an overall gross thickness of approximately 25 metres of intra-Muda sandstone, compared to a 7.3 metre reservoir sandstone seen in Mako South-1, providing volumetric upside potential for the field
• Pressure data confirm the same pressure system as Mako South-1 and Tambak-2
• Gas samples recovered from the reservoir confirm gas composition as seen in Mako South-1
• Gas-water contact found in the main upper sandstone unit circa 1.5 metres deeper than Mako South-1 and Tambak-2
As previously reported, the Tambak-1 well is designed as both an appraisal of the northeast flank of the Mako gas field as well as an exploration test of the Tambak prospect. An independent review by Gaffney Cline & Associates had previously ascribed gross 2C resources of 276 Bcf (48.78 MMboe) of recoverable dry gas in the Mako field with gross 3C resources of 392 Bcf (69.3 MMboe) representing additional field upside.
Coro management estimate that an increase in 2C resources of circa 100 Bcf is justified from the results of the successful appraisal drilling in both Tambak-1 and -2, representing a very significant value addition.
As a next step, the well will be drilled to a total depth of approximately 1,370 metres TVDSS in order to test the potential of the deeper Tambak prospect. Coro estimate Tambak as having a mid-case prospective resource potential of 250 Bcf and a geological chance of success of 45%. The Tambak-1 well is planned to be plugged and abandoned once operations are complete.
Mako as a large, shallow structural closure, extending more than 350 sq km. The field is 16 km from the WNTS pipeline system that supplied gas from Indonesia to Singapore.
(Source: Coro Energy)
Important News
- ORSTED – HEADWINDS ARE BLOWING ACROSS NEW JERSEY 02nd November 2023
- CHEVRON ACQUIRES HESS FOR $53 BILLION 24th October 2023
- EXXONMOBIL ACQUIRES PIONEER NATURAL RESOURCES 12th October 2023
- TEPCO – DISCHARGE OF FUKUSHIMA CONTAMINATED WATER TO THE OCEAN 27th August 2023
- NORWAY LOGS LARGEST HYDROCARBON DISCOVERY IN A DECADE 12th July 2023
- VOLOCOPTER AND ADP TO OFFER eVTOL SERVICES FOR THE 2024 OLYMPIC GAMES 25th June 2023